Tunnel Access in Controlled Mode

Thursday, 23.01.2025

Time
Description
Responsible
from 12:00 X08DB microscope (2 h) {{Cigdem}}

Tuesday, 21.01.2025

Time
Description
Responsible
08:00 - 10:00 Realignment / alignment check for 9 mm aperture Tapering Element upstream of 3HC {{Tino}}
08:00 - 10:00 Check ICT in BRTL {{Cigdem}}

Monday, 20.01.2025

Time
Description
Responsible
09:00 - 09:15 BPM Checks {{Fabio}}

Friday, 16.01.2025

Time
Description
Responsible
12:00 - 13:00 Check/Correction of BPM cabling {{Fabio}}
12:00 - 14:00 Realignment/alignment checks {{Karsten}}

Thursday, 15.01.2025

Time
Description
Responsible
07:00 - 14:00 Realignment of Superbends {{Karsten}}
ab 07:00 Turbo wieder einschalten (1h) {{Reno}}

Monday, 23.12.2024

Time
Description
Responsible
ab 08:00 X01DD Front End Work {{Arturo}}
07:30 - 08:00 Tunnel freimessen {{Fredy}}

Friday, 20.12.2024

Time
Description
Responsible
07:00 - 09:00 Abschluss des Ausheizens X01L + X02S: Messzellen Starten, Eckventile leicht schliessen, Trennen der Turbo-Pumpen vom gepumpten Rohr um zu vermeiden, dass die Ion-Pumps die Turbos pumpen. {{Reno}}
07:00 - 09:00 X01DD Front End Work {{Arturo}}

Thursday, 19.12.2024

Time
Description
Responsible
07:00 - 09:00 Abschluss des Ausheizens X08DB + X06DA: Messzellen Starten, Eckventile leicht schliessen, Trennen der Turbo-Pumpen vom gepumpten Rohr um zu vermeiden, dass die Ion-Pumps die Turbos pumpen. {{Reno}}
07:00 - 09:00 X01L + X02S NEG-Aktivierung, IGP starten, Rampe langsam runter bis 75C {{Reno}}
07:00 - 08:00 MIS Test Ventil ARS08-VVPG-5940, ARS03-VVPG-5940, Sektor 02, 10, 06 {{Natalia}} und {{Toni}}
07:00 - 09:00 X01DD Front End Work {{Cigdem}}, {{Arturo}}, {{Andrin}} and {{Istvan}}
08:00 - 09:00 Reparatur Vakuum Ventil:  X08SA, X08DA, X08DB, X12SA-FE-VVPG-000, ARS12-VVPG-1550 {{Peter}}

Wednesday, 18.12.2024

Time
Description
Responsible
07:00 - 09:00 Abschluss des Ausheizens X01DD: Messzellen Starten, Eckventile leicht schliessen, Trennen der Turbo-Pumpen vom gepumpten Rohr um zu vermeiden, dass die Ion-Pumps die Turbos pumpen. {{Reno}}
07:00 - 09:00 X08DB + X06DA NEG Aktivierung, IGP starten, Rampe langsam runter bis 75C {{Reno}}
07:30 - 09:00 Connect and test thermocouples for the MIS Straight 6,10,12
Connect and test vacuum valves S10, S08
{{Natalia}}

Tuesday, 17.12.2024

Time
Description
Responsible
07:00 - 09:00 Connect the motors and encoders for motion checks after front end bakeout. {{Cigdem}}
07:00 - 09:00 Check ECMC modules at X01DD {{Arturo}}
07:00 - 09:00 X01DD NEG Aktivierung, IGP starten, Rampe langsam runter bis 75C {{Reno}}
07:30 - 08:00 Wir möchten mit der Inbetriebnahme des Rings VCS vorankommen und müssen 5 Ventile, die uns Fehler anzeigen, überprüfen {{Natalia}} und {{Toni}}

Monday, 16.12.2024

Time
Description
Responsible
07:00 - 08:00 Entfernung der SU Messwagen für HF Konditionierung bei offenem Tunnel und SU Tunnelrundgang vor Strahlfreigabe {{Fredy}}
08:00 - 08:45 Info über das Vorgehen für Tunnelzutritt im Status «Überwacht». Treffpunkt: Mo 16.12.2024, 08:00, Ringtunnel Haupttüre Z54 (Achse 54). Es ist keine Anmeldung erforderlich {{Christine}}
08:45 - 09:15 Tunnelrundgang und Tunnel auf gesperrt {{Juri}}