Tunnel Access

Tuesday, 08.04.2025

Time
Description
Responsible
07:30 - 08:00 Freimessen durch SU (SLS-LOG 60587) {{OliverC}} und {{Rebecca}}
SHUTDOWN (DUO PLAN) {: colspan=3} &#8288 {: style="padding:0"} &#8288 {: style="padding:0"}

Tuesday, 01.04.2025

Time
Description
Responsible
07:30 - 08:00 Freimessen durch SU (SLS-LOG 60398) {{OliverC}} und {{Rebecca}}
08:00 - 12:00 Überwachter Zugang {: colspan=2} &#8288 {: style="padding:0"}

Tuesday, 25.03.2025

Time
Description
Responsible
07:30 - 08:00 Freimessen durch SU {{OliverC}}
08:00 - 09:00 Überwachter Zugang
09:00 - 12:00 Tunnel gesperrt, kein Strahl, PSYS Tests der Front End Shutter
12:00 - 15:00 Tunnel auf frei

Tuesday, 18.03.2025

Time
Description
Responsible
08:00 - 08:30 Freimessen durch SU {{OliverC}}
08:30 - 12:00 Hardware I/O Test X01DA
Hardware I/O Test PXIII
A. Di Giovanna
08:30 - 12:00 tenative: Alignment Sextupol Arc 06 K. Dreyer
08:30 - 12:00 FE- Vorbereitungen J. Mück
08:30 - 12:00 Überprüfung FE Slits/Filter X10DA S. Hitz
08:30 - 12:00 SD-Vorbereitungen 4h N. Gaiffi
08:30 - 12:00 Test Correctors Arc 04,05,06,08 10:00-11:00 C. Calzolaio
08:30 - 12:00 Wasserwächterblende austauschen 1h K. Zehnder
08:30 - 12:00 Überprüfung Schnellschlussventile X01DA & X10SA 2h M. Muser
08:30 - 12:00 ARC 3 Kicker Thermocouples adjustment 2h M. Dehler

Wednesday, 19.02.2025

Time
Description
ELOG
Responsible
07:00 - 08:00 Tunnel freimessen durch SU (access at door Z54) ... {{OliverC}}
SHUTDOWN (DUO PLAN) {: colspan=4} &#8288 {: style="padding:0"} &#8288 {: style="padding:0"} &#8288 {: style="padding:0"}

Monday, 17.02.2025

Time
Description
ELOG
Responsible
13:00 - 13:15 Tunnel freimessen durch SU (access at door Z54) ... {{OliverC}}
13:15 - 16:00 Realignment/alignment checks X01, e.g., taper downstream of kicker 4 ... {{Reno}}
13:15 - 16:00 Realignment of one triplet upstream of central triplet in ARS06 300 um towards outside SLS-LOG 60030 {{Karsten}}
13:15 - 16:00 Double check correct/full retraction of screen ARS01-DSCR-0750 SLS-LOG 60033 {{Cigdem}}

Friday, 14.02.2025

Time
Description
ELOG
Responsible
15:30 - 16:30 SU Begleitung für kurzen Zugang ... {{OliverC}}
15:30 - 16:30 Realignment/alignment checks X01, e.g., taper downstream of kicker 4 ... {{Reno}}

Tuesday, 11.02.2025

Time
Description
ELOG
Responsible
06:30 - 07:00 Tunnel freimessen durch SU (access at door Z54) ... {{OliverC}}
07:00 - 11:00 Triplet Alignment in ARC6 (4h) ... {{Karsten}}
07:00 - 08:00 Tunnelsteine X02DA prüfen, Cavity Heiz-Isoliermatten holen (1h) ... {{Reno}}
07:00 - 10:00 Kabel BPM Verbindungen anziehen (3h) ... M.Menghini
08:00 - 10:00 PS driver tests (no tunnel but reboot, not urgent)(1h) ... D. Zimoch/U. Zezula
08:00 - 10:00 Fix ND stage in X08DB ... {{Cigdem}}
07:00 - 11:00 Vorbereiten FE (4h) ... J.Mück

Tuesday, 04.02.2025

Time
Description
ELOG
Responsible
06:30 - 07:00 Tunnel freimessen durch SU (access at door Z54) ... {{OliverC}}
07:00 - 11:00 Reconfigure/reboot timing system (not in tunnel) ... {{Romain}}
07:00 - 11:00 Reconfigure/reboot MIS (not in tunnel) ... {{MartinG}}
07:00 - 11:00 Camera checks X08 (2h) ... {{Cigdem}}
07:00 - 11:00 Kontrolle Kavität 3HC Eisbildung (15 Min) ... D. Deak
07:00 - 11:00 Vorbereitung FE, ID Grundplatten prüfen 1h ... {{Reno}}
07:00 - 11:00 Investigation dark current linac gun ... {{Paolo}}
07:00 - 11:00 Heizmaterial X02S/X02D/X06S ... J. Mück
07:00 - 11:00 Kabel BPM Verbindungen anziehen ... M. Menghini

Wednesday, 29.01.2025

Time
Description
ELOG
Responsible
07:30 - 08:00 Booster RF leakage measurement (access at door Z54) ... {{OliverC}} and {{Lukas}}
08:00 - 08:10 Tunnel freimessen durch SU (access at door Z54) ... {{OliverC}}
08:10 - 11:00 MIS PLC reboot and Checks ... {{Tony}}
08:10 - 11:00 Improve the BPM system shielding ... {{Fabio}} and {{Boris}}
08:10 - 11:00 Check super-3HC Eisbildung ... {{Christian}}
08:10 - 11:00 Check PCTs and X08DB ... {{Cigdem}}
08:10 - 11:00 length of below at 3HC, XBPM Überprüfung ... {{Reno}}
08:10 - 11:00 Lecktest X06S, X01D ... Johannes Mück
10:00 - 11:00 Aufnahme Magnete Straights ... P. Lerch

Monday, 27.01.2025

Time
Description
ELOG
Responsible
14:20 - 14:40 Check BPM first 3 to 4 BPMs in ARC09 Dev-LOG 2383 {{Fabio}}
13:00 - 14:00 Check BPM ARC08-DBPM-0180 Dev-LOG 2383 {{Fabio}}
13:00 - 14:00 Check booster cavity RF leakage RF-LOG 1919 {{Lukas}}

Thursday, 23.01.2025

Time
Description
Responsible
from 12:00 X08DB microscope (2 h) {{Cigdem}}

Tuesday, 21.01.2025

Time
Description
Responsible
08:00 - 10:00 Realignment / alignment check for 9 mm aperture Tapering Element upstream of 3HC {{Tino}}
08:00 - 10:00 Check ICT in BRTL {{Cigdem}}

Monday, 20.01.2025

Time
Description
Responsible
09:00 - 09:15 BPM Checks {{Fabio}}

Friday, 17.01.2025

Time
Description
Responsible
12:00 - 13:00 Check/Correction of BPM cabling {{Fabio}}
12:00 - 14:00 Realignment/alignment checks {{Karsten}}

Thursday, 16.01.2025

Time
Description
Responsible
07:00 - 14:00 Realignment of Superbends {{Karsten}}
ab 07:00 Turbo wieder einschalten (1h) {{Reno}}

Monday, 23.12.2024

Time
Description
Responsible
ab 08:00 X01DD Front End Work {{Arturo}}
07:30 - 08:00 Tunnel freimessen {{Fredy}}

Friday, 20.12.2024

Time
Description
Responsible
07:00 - 09:00 Abschluss des Ausheizens X01L + X02S: Messzellen Starten, Eckventile leicht schliessen, Trennen der Turbo-Pumpen vom gepumpten Rohr um zu vermeiden, dass die Ion-Pumps die Turbos pumpen. {{Reno}}
07:00 - 09:00 X01DD Front End Work {{Arturo}}

Thursday, 19.12.2024

Time
Description
Responsible
07:00 - 09:00 Abschluss des Ausheizens X08DB + X06DA: Messzellen Starten, Eckventile leicht schliessen, Trennen der Turbo-Pumpen vom gepumpten Rohr um zu vermeiden, dass die Ion-Pumps die Turbos pumpen. {{Reno}}
07:00 - 09:00 X01L + X02S NEG-Aktivierung, IGP starten, Rampe langsam runter bis 75C {{Reno}}
07:00 - 08:00 MIS Test Ventil ARS08-VVPG-5940, ARS03-VVPG-5940, Sektor 02, 10, 06 {{Natalia}} und {{Tony}}
07:00 - 09:00 X01DD Front End Work {{Cigdem}}, {{Arturo}}, {{Andrin}} and {{Istvan}}
08:00 - 09:00 Reparatur Vakuum Ventil:  X08SA, X08DA, X08DB, X12SA-FE-VVPG-000, ARS12-VVPG-1550 {{Peter}}

Wednesday, 18.12.2024

Time
Description
Responsible
07:00 - 09:00 Abschluss des Ausheizens X01DD: Messzellen Starten, Eckventile leicht schliessen, Trennen der Turbo-Pumpen vom gepumpten Rohr um zu vermeiden, dass die Ion-Pumps die Turbos pumpen. {{Reno}}
07:00 - 09:00 X08DB + X06DA NEG Aktivierung, IGP starten, Rampe langsam runter bis 75C {{Reno}}
07:30 - 09:00 Connect and test thermocouples for the MIS Straight 6,10,12
Connect and test vacuum valves S10, S08
{{Natalia}}

Tuesday, 17.12.2024

Time
Description
Responsible
07:00 - 09:00 Connect the motors and encoders for motion checks after front end bakeout. {{Cigdem}}
07:00 - 09:00 Check ECMC modules at X01DD {{Arturo}}
07:00 - 09:00 X01DD NEG Aktivierung, IGP starten, Rampe langsam runter bis 75C {{Reno}}
07:30 - 08:00 Wir möchten mit der Inbetriebnahme des Rings VCS vorankommen und müssen 5 Ventile, die uns Fehler anzeigen, überprüfen {{Natalia}} und {{Tony}}

Monday, 16.12.2024

Time
Description
Responsible
07:00 - 08:00 Entfernung der SU Messwagen für HF Konditionierung bei offenem Tunnel und SU Tunnelrundgang vor Strahlfreigabe {{Fredy}}
08:00 - 08:45 Info über das Vorgehen für Tunnelzutritt im Status «Überwacht». Treffpunkt: Mo 16.12.2024, 08:00, Ringtunnel Haupttüre Z54 (Achse 54). Es ist keine Anmeldung erforderlich {{Christine}}
08:45 - 09:15 Tunnelrundgang und Tunnel auf gesperrt {{Juri}}