Tunnel Access in Controlled Mode
Wednesday, 29.01.2025
Time |
Description | Responsible |
|---|---|---|
08:00 - 11:00 |
MIS PLC reboot and Checks | {{Tony}} |
Thursday, 23.01.2025
Time |
Description | Responsible |
|---|---|---|
from 12:00 |
X08DB microscope (2 h) | {{Cigdem}} |
Tuesday, 21.01.2025
Time |
Description | Responsible |
|---|---|---|
08:00 - 10:00 |
Realignment / alignment check for 9 mm aperture Tapering Element upstream of 3HC | {{Tino}} |
08:00 - 10:00 |
Check ICT in BRTL | {{Cigdem}} |
Monday, 20.01.2025
Time |
Description | Responsible |
|---|---|---|
09:00 - 09:15 |
BPM Checks | {{Fabio}} |
Friday, 17.01.2025
Time |
Description | Responsible |
|---|---|---|
12:00 - 13:00 |
Check/Correction of BPM cabling | {{Fabio}} |
12:00 - 14:00 |
Realignment/alignment checks | {{Karsten}} |
Thursday, 16.01.2025
Time |
Description | Responsible |
|---|---|---|
07:00 - 14:00 |
Realignment of Superbends | {{Karsten}} |
ab 07:00 |
Turbo wieder einschalten (1h) | {{Reno}} |
Monday, 23.12.2024
Time |
Description | Responsible |
|---|---|---|
ab 08:00 |
X01DD Front End Work | {{Arturo}} |
07:30 - 08:00 |
Tunnel freimessen | {{Fredy}} |
Friday, 20.12.2024
Time |
Description | Responsible |
|---|---|---|
07:00 - 09:00 |
Abschluss des Ausheizens X01L + X02S: Messzellen Starten, Eckventile leicht schliessen, Trennen der Turbo-Pumpen vom gepumpten Rohr um zu vermeiden, dass die Ion-Pumps die Turbos pumpen. | {{Reno}} |
07:00 - 09:00 |
X01DD Front End Work | {{Arturo}} |
Thursday, 19.12.2024
Time |
Description | Responsible |
|---|---|---|
07:00 - 09:00 |
Abschluss des Ausheizens X08DB + X06DA: Messzellen Starten, Eckventile leicht schliessen, Trennen der Turbo-Pumpen vom gepumpten Rohr um zu vermeiden, dass die Ion-Pumps die Turbos pumpen. | {{Reno}} |
07:00 - 09:00 |
X01L + X02S NEG-Aktivierung, IGP starten, Rampe langsam runter bis 75C | {{Reno}} |
07:00 - 08:00 |
MIS Test Ventil ARS08-VVPG-5940, ARS03-VVPG-5940, Sektor 02, 10, 06 | {{Natalia}} und {{Tony}} |
07:00 - 09:00 |
X01DD Front End Work | {{Cigdem}}, {{Arturo}}, {{Andrin}} and {{Istvan}} |
08:00 - 09:00 |
Reparatur Vakuum Ventil: X08SA, X08DA, X08DB, X12SA-FE-VVPG-000, ARS12-VVPG-1550 | {{Peter}} |
Wednesday, 18.12.2024
Time |
Description | Responsible |
|---|---|---|
07:00 - 09:00 |
Abschluss des Ausheizens X01DD: Messzellen Starten, Eckventile leicht schliessen, Trennen der Turbo-Pumpen vom gepumpten Rohr um zu vermeiden, dass die Ion-Pumps die Turbos pumpen. | {{Reno}} |
07:00 - 09:00 |
X08DB + X06DA NEG Aktivierung, IGP starten, Rampe langsam runter bis 75C | {{Reno}} |
07:30 - 09:00 |
Connect and test thermocouples for the MIS Straight 6,10,12 Connect and test vacuum valves S10, S08 |
{{Natalia}} |
Tuesday, 17.12.2024
Time |
Description | Responsible |
|---|---|---|
07:00 - 09:00 |
Connect the motors and encoders for motion checks after front end bakeout. | {{Cigdem}} |
07:00 - 09:00 |
Check ECMC modules at X01DD | {{Arturo}} |
07:00 - 09:00 |
X01DD NEG Aktivierung, IGP starten, Rampe langsam runter bis 75C | {{Reno}} |
07:30 - 08:00 |
Wir möchten mit der Inbetriebnahme des Rings VCS vorankommen und müssen 5 Ventile, die uns Fehler anzeigen, überprüfen | {{Natalia}} und {{Tony}} |
Monday, 16.12.2024
Time |
Description | Responsible |
|---|---|---|
07:00 - 08:00 |
Entfernung der SU Messwagen für HF Konditionierung bei offenem Tunnel und SU Tunnelrundgang vor Strahlfreigabe | {{Fredy}} |
08:00 - 08:45 |
Info über das Vorgehen für Tunnelzutritt im Status «Überwacht». Treffpunkt: Mo 16.12.2024, 08:00, Ringtunnel Haupttüre Z54 (Achse 54). Es ist keine Anmeldung erforderlich | {{Christine}} |
08:45 - 09:15 |
Tunnelrundgang und Tunnel auf gesperrt | {{Juri}} |