SLS Operation Statistics Weekly and anual operation statistics for the SLS are given here main.html
toc

??? info "Definitions used for the presented statistics" * Scheduled-user-time: this time is scheduled upfront and distributed between the accepted user proposals * Reserve-time: additional user time, provided to compensate for beam outages (often scheduled mid and end of year, not always used for user operation) * User-operation: Scheduled-user-time + Reserve-time * Downtime: time between beam loss (Ibeam < 20 mA) and full recovery (Ibeam >= Inominal = 400 mA) during user-operation * Short-uptime-rule: if two beam outages have less than 1 hour of uptime in between, it is counted as one long downtime. * Total-downtime: sum of all individual downtimes of one year * Total-beam-time sum of all scheduled beam times (user, beamline, machine, ...) * Machine development sum of scheduled beam times (user, beamline, machine, ...) * Delivered-beam-time: User-operation - Total-downtime * Number-of-faults: incidence count of all individual Downtimes * Injector-outage-time: time between beam drop (Ibeam < 390 mA) and full recovery (Ibeam >= Inominal = 400 mA) during user-operation * Number-of-distortions: incidence count of faults and beam drops, orbit feedback failures, low beam-lifetimes (tau < 8 hours), beam blow ups (sigy > 15 um) and distorted filling patterns * Availability: Delivered-beam-time / User-operation * Availability after compensation: Delivered-beam-time / Scheduled-user-time. * MTBF: Mean Time Between Failures = User-operation / (Number-of-faults + 1) * MTTR: Mean Time To Recover = Total-downtime / Number-of-faults * MTBD: Mean Time Between Distortions = User Time / Number-of-distortion

More information is available in [Phys. Rev. Accel. Beams 19, 082802](https://doi.org/10.1103/PhysRevAccelBeams.19.082802) and [here](http://gfa-operation.intranet.psi.ch/kr/sls/sls_opstat.php).

2025

DUO Schedule
Time Hours %
Scheduled-user-time 912 10.5
Reserve-time 48 0.5
User operation 960 11.0
User operation 960 11.0
Beamline development 1824 20.8
Machine development 3192 36.4
Total beam time 5976 68.2
Total beam time 5976 68.2
Shutdown 2784 31.8
Total 8760 100.0
Delivery for total beam time
Average beam current 299 mA
Circulating beam dose 1590 Ah
Injected charge 659.3 μC
Quarterly Beam Dose for Dosimetry
Q1 (11.12.2024 - 19.03.2025) 22.4 Ah
Q2 (19.03.2025 - 18.06.2025) 450.1 Ah
Q3 (18.06.2025 - 17.09.2025) 499.7 Ah
Q4 (17.09.2025 - 10.12.2025) 512.5 Ah
Delivery for User Operation
User operation 960 hours
Total downtime 54.1 hours
Number-of-faults 49
Availability 94.4 %
Availability after compensation 99.3 %
MTBF 19.2 hours
MTTR 1.1 hours