Minutes of the SLS 2.0 Beam Development Meetings
-## 20/01/2025
+## 27/01/2025
**Participants:**
{{Boris}}, {{Micha}}, {{Masamitsu}}, {{Jesus}}, {{Volker}}, {{Cigdem}}, {{Jonas}}, {{Felix}}, {{Lukas}}, {{Hans}}, {{Simona}}, {{Micha}}
+-->
+
+
+1. **Introduction**
+
+ * **Approval of last minutes**
+ * All those present confirm the [minutes](https://sls.gitpages.psi.ch/bdm/minutes/#20012025) of the last meeting
+
+ * **Communication**
+ * Please send shift requests for coming week until Friday then I can prepare preliminary schedule for discussion in the meeting
+ * For the convenience of the operators the machine shift and controlled tunnel access tables are located on dedicated subsites of the SLS 2.0 Operations Management website:
+ * [Tunnel Access](https://sls.gitpages.psi.ch/tunnel/)
+ * [Machine Shifts](https://sls.gitpages.psi.ch/shifts/)
+ * Machine Shift Reports
+ * Please prepare shift reports in elog. These will be linked in the machine shifts table.
+ * For SLS 2.0 commissioning shifts a template for the elog entries is prepared and will be automatically loaded when chosing the project "SLS-2 Commissioning" in the SLS Development Logbook
+
+2. **Reports**
+
+ * **Linac/LTB Optimization** by {{Volker}}
+ * ...
+
+ * **Booster/BRTL Optimization** by {{Jonas}}
+ * ...
+
+ * **Linac/LTB Optimization** by {{Volker}}
+ * ...
+
+ * **Storage Ring Commissioning** by {{Masamitsu}}
+ * ...
+
+ * **Injection Elements** by {{Martin}}
+ * ...
+
+ * **RF** by {{Lukas}}
+ * ...
+
+ * **Diagnostics** by {{Cigdem}}
+ * ...
+
+ * **BPMs** by {{Boris}}
+ * ...
+
+* **Remark** from {{Felix}}
+ * Wait with in advance request schedule / planning until we are out of the woods with the commissioning, i.e, reproducibly can achieve stored and accumulate beam
+ * [Shift schedule](https://sls.gitpages.psi.ch/shifts/)
+
+ * **General commissioning schedule for KW05**
+ * Operators start RF and Booster until 7:30
+ * Operator training from 7:30 until 8:30
+ * Linac/Booster Optimization until 10:00
+ * Storage Ring Commissioning until 18:00
+ * Boris BPM development in parallel and after 18:00
+
+
+ * **To Be Investigated**
+ * Timing
+
+ * **Tunnel Access**
+ * Wednesday morning 8:00 until 11:00 for MIS PLC reboot
+
+Minutes written by {{Felix}}
+
+## 20/01/2025
+
+**Participants:**
+{{Boris}}, {{Micha}}, {{Masamitsu}}, {{Jesus}}, {{Volker}}, {{Cigdem}}, {{Jonas}}, {{Felix}}, {{Lukas}}, {{Hans}}, {{Simona}}, {{Micha}}
@@ -122,7 +188,7 @@
* low level panels of VME EVRs are unfortunately not available
* Absence of timing expert unfortunate, updating config file of EVR not yet successful despite involving official substitute for timing expert
* running without backup for thin septum pulser
- * high voltage power supplies for booster injection kickers ordered but not yet here (
+ * high voltage power supplies for booster injection kickers ordered but not yet here
* main and backup failed during commissioning
* 6 months lead time
@@ -195,23 +261,6 @@ Minutes written by {{Felix}}
## 13/01/2025
**Participants:**
-
{{Cigdem}}, {{Felix}}, {{Jesus}}, {{Jonas}}, {{Lukas}}, {{Martin}}, {{Masamitsu}}, {{Micha}}, {{Michael}}