diff --git a/docs/bdm/minutes/index.md b/docs/bdm/minutes/index.md index 0926795..d8a38b8 100644 --- a/docs/bdm/minutes/index.md +++ b/docs/bdm/minutes/index.md @@ -1,6 +1,6 @@

Minutes of the SLS 2.0 Beam Development Meetings

-## 20/01/2025 +## 27/01/2025 **Participants:** {{Boris}}, {{Micha}}, {{Masamitsu}}, {{Jesus}}, {{Volker}}, {{Cigdem}}, {{Jonas}}, {{Felix}}, {{Lukas}}, {{Hans}}, {{Simona}}, {{Micha}} +--> + + +1. **Introduction** + + * **Approval of last minutes** + * All those present confirm the [minutes](https://sls.gitpages.psi.ch/bdm/minutes/#20012025) of the last meeting + + * **Communication** + * Please send shift requests for coming week until Friday then I can prepare preliminary schedule for discussion in the meeting + * For the convenience of the operators the machine shift and controlled tunnel access tables are located on dedicated subsites of the SLS 2.0 Operations Management website: + * [Tunnel Access](https://sls.gitpages.psi.ch/tunnel/) + * [Machine Shifts](https://sls.gitpages.psi.ch/shifts/) + * Machine Shift Reports + * Please prepare shift reports in elog. These will be linked in the machine shifts table. + * For SLS 2.0 commissioning shifts a template for the elog entries is prepared and will be automatically loaded when chosing the project "SLS-2 Commissioning" in the SLS Development Logbook + +2. **Reports** + + * **Linac/LTB Optimization** by {{Volker}} + * ... + + * **Booster/BRTL Optimization** by {{Jonas}} + * ... + + * **Linac/LTB Optimization** by {{Volker}} + * ... + + * **Storage Ring Commissioning** by {{Masamitsu}} + * ... + + * **Injection Elements** by {{Martin}} + * ... + + * **RF** by {{Lukas}} + * ... + + * **Diagnostics** by {{Cigdem}} + * ... + + * **BPMs** by {{Boris}} + * ... + +* **Remark** from {{Felix}} + * Wait with in advance request schedule / planning until we are out of the woods with the commissioning, i.e, reproducibly can achieve stored and accumulate beam + * [Shift schedule](https://sls.gitpages.psi.ch/shifts/) + + * **General commissioning schedule for KW05** + * Operators start RF and Booster until 7:30 + * Operator training from 7:30 until 8:30 + * Linac/Booster Optimization until 10:00 + * Storage Ring Commissioning until 18:00 + * Boris BPM development in parallel and after 18:00 + + + * **To Be Investigated** + * Timing + + * **Tunnel Access** + * Wednesday morning 8:00 until 11:00 for MIS PLC reboot + +Minutes written by {{Felix}} + +## 20/01/2025 + +**Participants:** +{{Boris}}, {{Micha}}, {{Masamitsu}}, {{Jesus}}, {{Volker}}, {{Cigdem}}, {{Jonas}}, {{Felix}}, {{Lukas}}, {{Hans}}, {{Simona}}, {{Micha}} @@ -122,7 +188,7 @@ * low level panels of VME EVRs are unfortunately not available * Absence of timing expert unfortunate, updating config file of EVR not yet successful despite involving official substitute for timing expert * running without backup for thin septum pulser - * high voltage power supplies for booster injection kickers ordered but not yet here ( + * high voltage power supplies for booster injection kickers ordered but not yet here * main and backup failed during commissioning * 6 months lead time @@ -195,23 +261,6 @@ Minutes written by {{Felix}} ## 13/01/2025 **Participants:** - {{Cigdem}}, {{Felix}}, {{Jesus}}, {{Jonas}}, {{Lukas}}, {{Martin}}, {{Masamitsu}}, {{Micha}}, {{Michael}}