Downtime 03.02.2020
This commit is contained in:
@ -54,5 +54,8 @@ The table below shows a description for the next Scheduled Downtime:
|
||||
|
||||
| From | To | Affected Service/s | Description |
|
||||
| :------------: | --------- | :----------------------------- | :----------------------------------------------------------------- |
|
||||
| *10..01.2020 9h* | *12.01.2020 20h* | All Services | PSI IT yearly shutdown. Major Firmware and Service Upgrages on Merlin |
|
||||
| *03.02.2020 9h* | *03.02.2020 10h* | Slurm Batch System | Fix GPU type problem. Might be sporadic Slurm service disruption. |
|
||||
|
||||
* **Note**: Only the Slurm batch system will be affected. We expect a sporadic disruption, where users will not be able to submit new jobs for
|
||||
few seconds. Another possible problem is that some jobs might not be scheduled correctly and in the worst case will be cancelled. Running jobs
|
||||
should not be affected.
|
||||
|