diff --git a/docs/2._Services_Portfolio/Initiatives/04_areadetector.md b/docs/2._Services_Portfolio/Initiatives/04_areadetector.md
index aaeaf980..d32027ed 100644
--- a/docs/2._Services_Portfolio/Initiatives/04_areadetector.md
+++ b/docs/2._Services_Portfolio/Initiatives/04_areadetector.md
@@ -21,8 +21,8 @@ Alongside driver testing, we updated the timing and synchronization setup:
- **Synchronization:** Updated the infrastructure to support PTP synchronization for GigE cameras where supported. For scientific cameras without PTP, a back-trigger method is used where the camera sends a trigger signal back to be digitized by a Beckhoff module.
## Layout
-
-### Current architecture
+
+### Legacy architecture
```mermaid
flowchart LR
subgraph Legacy ["Current Architecture (Per-Server EVR)"]
@@ -57,6 +57,37 @@ flowchart LR
FAN1 -->|"Triggers"| CAMS1
end
```
+### New architecture
+```mermaid
+flowchart LR
+ subgraph Proposed ["Proposed Architecture (Centralized Timing)"]
+ direction LR
+ EVT_NEW["EVT"]
+
+ subgraph Rack2 ["Camera Rack"]
+ direction TB
+ subgraph TS ["Timing Server"]
+ EVR_NEW["EVR"]
+ BECKHOFF["BECKHOFF IOC"]
+ end
+ CN1["Camera node"]
+ CN2["Camera node"]
+ CN3["Camera node"]
+ end
+
+ FAN_NEW["EVR fan
Output: 16 LEMO / 8 RJ45
Input: 2 LEMO"]
+ CAMS2["Cameras"]
+
+ EVT_NEW --> EVR_NEW
+ EVR_NEW -->|"ZMQ stream"| FAN_NEW
+ TS -->|"PID over ZMQ"| CN1
+ TS -->|"PID over ZMQ"| CN2
+ TS -->|"PID over ZMQ"| CN3
+
+ CN1 <-->|"Data / Control"| CAMS2
+ FAN_NEW -->|"Triggers"| CAMS2
+ end
+```
## Schedule
The production rollout prioritizes the oldest hardware (**Gen 8** servers) first before moving to newer generations. Rollout progress and individual server migrations are tracked in [SFELPHOTON-1870](https://psich.atlassian.net/browse/SFELPHOTON-1870).